Project Timeline


In April 2014, Gulf LNG Liquefaction Company, LLC (GLLC) awarded a contract to KBR to provide FERC FEED engineering and FERC report pre-filing services for two liquefaction trains and associated facilities based on KBR’s proven reference design using APCI C3MR Technology. On May 21, 2014, GLLC received approval from FERC to initiate the NEPA pre-filing process and on June 19, 2015 GLLC filed its formal FERC application. GLLC has responded to all outstanding FERC data requests as of January 2017 and FERC is now engaged in the process of preparing a draft Environmental Impact Statement. GLLC also continues to work with all other federal and local agencies to provide information necessary for related approvals. We expect to begin the next phase of engineering (FEED) once commercial commitments within the export market are obtained.