East Line

Kinder Morgan’s East Line consists of two parallel lines originating in El Paso, Texas, and ending in Phoenix, Arizona. In 2007, Kinder Morgan completed a major expansion on its East Line system which replaced almost 130 miles of 8-inch diameter pipeline between El Paso and Tucson with new state-of-the-art 16-inch diameter pipe, increasing capacity on the East Line to over 200,000 barrels per day.  In 2006, Kinder Morgan completed the first phase of its pipeline expansion into Arizona by replacing more than 230 miles of 8-inch diameter pipeline between El Paso and Phoenix, Ariz., with new 16- and 12-inch diameter pipe.  The expansion project also included the construction of a new pump station and a 490,000 barrel tank facility near El Paso, and upgrades to existing stations and terminals between El Paso and Phoenix.